The Webuild-led consortium constructing a brand new 6km-long breakwater off the Port of Genoa has notched up two notable milestones: the sinking of its tenth caisson and the completion of 34,000 gravel columns to stabilise the seabed.
The PerGenova Breakwater Consortium is 40% owned by Webuild and consists of Fincantieri Infrastructure Opere Marittime, Fincosit, and Sidra.
The Western Ligurian Sea Port Authority awarded the €928m contract to it in October 2022.
It is going to push the outer barrier of the harbour 450m farther out to sea from the present breakwater in order that ultra-large container ships can dock and switch in calm water.
The enlargement of the harbour space is anticipated to spice up site visitors by as much as 30% between 2027, when the primary, 4km-long part is because of be completed, and 2030, when the second, 2km-long part is completed.
Making ready the seabed
With the tenth caisson in place, the consortium will begin prefabricating the bigger caissons, that are as much as 67m lengthy, 35m large, and almost 34m excessive.
They’ll be constructed contained in the “Tronds Barge 33” prefabrication dock in Vado Ligure, some 54km alongside the coast west of Genoa, barged to location and sunk to depths of as much as 50m.
To stabilise the seabed, the consortium has accomplished 34,000 gravel columns, greater than half the whole deliberate.
Positioned at depths of between 25m and 50m, they’re simply over a metre in diameter and 13.5m deep.
They’re created from a layer of greater than two million tonnes of gravel, principally from Spain, beforehand laid on the seabed.

The consortium makes use of eight vibroflot units: 20m-plus-long needle-shaped devices that steadily penetrate the seabed, breaking the soil with jets of pressurised water to make holes for the gravel to fall into for compaction.
Crews of greater than 450 folks work from three pontoons, the biggest greater than 150m lengthy, with cranes measuring as much as 40m in peak.
€4.2bn earnings increase
The brand new breakwater will enable ships as much as 400m in size to entry the port, boosting its contribution to the Rhine-Alpine Hall of the EU’s Trans-European Transport Community.
The port authority expects the enlargement to result in a €4.2bn increase in earnings from container site visitors, port rights, and taxes.
• Subscribe right here to get tales about development around the globe in your inbox 3 times every week
Additional studying
- Webuild consortium to broaden Genoa port with 6km breakwater
- Work begins on €928m breakwater to remodel Port of Genoa
The publish Webuild crew hits milestones on large Genoa breakwater appeared first on World Development Evaluation.